fbpx
< BACK TO NEWSROOM & EVENTS

RENO’S AT BIBRA LAKE – Here’s everything you need to know!

Exciting times await you as a Bibra Lake member! Each week, get the latest on how our renovations will impact you, right here! Visit this page for updates, schedule changes and everything you need to stay in the know and keep your fitness routine on track.

Update : 18 November 2024

We have an exciting announcement to make – Christmas really has come early for you Bibra Lake. Look out for our email update to you, you don’t want to miss this one!

For now, we can confirm that the wait is over! We’re excited to announce that Bibra Lake is kicking off a 3 stage upgrade plan to bring our BRAND NEW equipment to the gym floor! Over 70 pieces have arrived all the way from the USA, and we can’t wait to share them with you. From pin loaded to plate loaded, get ready to dive into our new playground!  

Here’s what you need to know 

Stage 1: Out with the Old, In with the New From Friday 22nd November – we’ll begin drip feeding some of the smaller new pieces of equipment on to the gym floor. This will be done very slowly and gradually across this week, with minimal impact to members. Please feel free to enjoy the gym without any disruption during this week.

GYM CLOSURE Saturday 30th November (8am) to Sunday, 1st December (Midnight) we will begin the main transfer of equipment to the gym floor, which will require us to temporarily close the area over the weekend. During this time, you’ll still have full access to the Watsons Gym located at the entrance to the Bibra Lake Club, as well as access to our ROAR Active sister Clubs at Canning Vale, Cockburn and Jandakot. We want to let you know too, that while this initial setup will get the new equipment on the floor sooner, the design and layout you see in Stage 1 won’t be the final gym floor arrangement. This initial Stage 1 move will only see about 70% of our new equipment roll out.

We still have a Wall of Squat Racks, New Functional Training Zone, Dedicated Warm Up area, flooring, mirrors, lighting and much more to come in the following stages. We can assure you that by stage 3, our fresh design will optimise your workout flow, but with it being such a large operation, we need to roll it out in stages to minimise disruption! We’re working hard to give you early access to these upgrades, with additional adjustments coming in Stages 2 and 3. Stay tuned for more updates as we progress through each stage – and in the meantime, enjoy this first phase of our Bibra Lake renovation journey!

Update : 11 November 2024

Did you see our sneak peak of all the equipment we have coming your way?? The team are working hard behind the scenes at getting these pieces put together in time for a little early Christmas present for you all as our valued Bibra Lake members. Keep checking here for all the updates. This announcement is going to be huge!

Update : 4 November 2024

Have you seen our sea containers, our new equipment has landed on site! Get excited Bibra Lake, we cannot wait to show you what is planned for your gym experience, COMING SOON!

We also have BIG news just in! Exciting Improvements are Coming to Our Aquatics Area! We’re excited to announce that from Monday, 2nd December 2024 to Sunday, 12th January 2025, we’ll be embarking on an exciting journey to enhance your Aquatics experience. During this time, our entire Indoor Aquatics area, including the Recovery Zone, will be temporarily CLOSED to undergo a significant transformation.

Here’s what you can look forward to:

  • New flooring around the indoor and kids’ pools, bringing a fresh and modern look.
  • The Sauna also sees new flooring installed, alongside restoration to all wood seating, walls and ceiling.
  • A complete makeover of the Steam Room, featuring new seating, flooring and newly tiled walls.
  • New wet deck grating around the Indoor Pool, Kids’ Pool and Spa for added safety and comfort.
  • An update to the Recovery Zone flooring, creating an even more relaxing atmosphere.
  • Upgraded flooring to the entry points to the male and female showers, giving the space a new feel.
  • Poolside showers will also get a fresh upgrade with brand new flooring.

While these exciting upgrades are taking place, you’ll still be able to enjoy our Outdoor Pool, which will remain open for your convenience. To ensure accessibility, we’re installing a custom built staircase, similar to the one in the Indoor Pool. Plus, since it’s Summer, there’s no need for pool heating, so you can dive in and cool off with ease!

We can’t wait to unveil these incredible improvements and provide you with an even better Aquatics experience in 2025! All this and more, coming soon!

Update: 28 October 2024

We have some big news! Our NEW equipment lands in port this week meaning are one step closer to delivering you with 70 pieces of the latest and newest equipment, all the way from the USA! We will have big trucks and containers landing in the rear carpark any day…from here, we need to build the equipment pieces before they will arrive on the gym floor over the coming month. Get excited Bibra Lake, the wait is almost over!

You might also notice our new Shower block is taking shape nicely. Check it out if you haven’t already poolside.

There are also some very big cement panels that are being installed over the coming week to the rear of RBG. We thank you for your patience as we get set to build something pretty amazing out there for your enjoyment. Remember, our venue remains open over the weekend for your enjoyment, plus during the week for inside bookings only.


Update: 21 October 2024

No real changes this week to the member eye, but trust us, there is lots happening around the grounds!

Please keep checking back here for all the updates, it is your go to for all things “Renos at Bibra Lake”.


Update : 14 October 2024

We have a big week planned, but all with minimal (if any!) impact to our members. Please remember, this page is your go to for all things on the “Renovation” front.

The best really is yet to come! Get excited – we sure are!


Update : 7 October 2024

Our works continue into this week…it’s all starting to happen! You asked, we listened—and now, it’s out with the old and in with the new at ROAR Bibra Lake!

Please keep checking this page for the latest updates and exciting developments!


Update : 30 September 2024

This week sees a lot of work behind the scenes by our incredible Maintenance Team. Whilst there is not any scheduled disruptions planned to our valued members, why not take this opportunity to have a look at our new sample piece of equipment in the main entry foyer, you can’t miss it! This is only the beginning of what’s to come! Get excited Bibra Lake, this renovation is going to be HUGE and we cannot wait!


Update: 24 September 2024

Works continue into this week with slab pours for our exciting new spaces taking place.

On Wednesday 25th, as we eagerly await our new gym floor revamp that’s coming soon!, we will see a temporary new sled track installed. Remember, this one is just a temporary replacement, just wait until you see the new black and white ROAR one we have ordered for our new space!  We anticipate to see these works carried out on the Wednesday only, with the sled track fully operational again from Thursday.

All this and more, coming soon!


Update : 16 September 2024

Thank you to all our valued members who adapted to the modified carpark works over the past few weeks. The good news is our works to the carpark are complete!

Remember, all this and more is all part of a bigger, better plan for your future enjoyment as we work to make our facilities even more amazing for you as a Bibra Lake member.


*Important Update: Carpark Reopening Delayed

Due to the wet weather conditions experienced this week, the completion of the carpark works will be delayed. The carpark is now expected to reopen next Friday, instead of the previously planned Monday. We appreciate your patience and understanding as we work through these unexpected changes.

Update : 9 September 2024

Our modified carpark works are almost over! We thank you for your patience over the past couple of weeks to see these works completed. Although the weather last week did put us back a week, the good news is we are on track to reopen this coming Friday. Until this time, the carpark will continue to remain restricted with alternate entry and exit points.


Update : 2 September 2024

Thank you to all our valued members who have adapted to the modified carpark works over the past week. The good news is we are on track to be finished these works on time! We also hope to have the main entry to the facility back open towards the end of the week.

Your patience and understanding is appreciated. Trust us, it’s all part of a bigger, better plan for your future enjoyment.


Update : 26 August 2024

CARPARK WORKS : Important reminder for all our valued members:

Starting on Monday, 26th August, temporary Parking Adjustments will be in place that will result in the following temporary changes.

  • Commencing Monday, 26th August, several parking bays to the rear of the building will be restricted as we begin carpark works as part of our exciting building works. 
  • Temporary fencing will be installed as we facilitate the trench work for the installation of the main services underground. Delivery of materials and machinery will commence this week, so please be mindful of these dedicated bays.
  • Entry and exit to the main driveway will also be modified. Access to the front carpark will be via the entry driveway in front of Repco only and to the rear, via Broadmeadows Street (which runs off Geelong Court).
  • The carpark area will have restricted access for approximately 14 days as we carry out these works.
  • Due to the scope of the works, RFX Athletic members please also be aware that the side rollerdoor will no longer be operational for any upcoming WODs.

We understand this may be a temporary inconvenience to you, but we promise it’s all part of a bigger, better plan for your future enjoyment. Your patience and co-operation is appreciated as we work towards making our facilities even more amazing!


Update: 20 August 2024

It’s all starting to happen! You asked, we listened—and now, it’s out with the old and in with the new at ROAR Bibra Lake!

Have you seen our brand new piece of Equipment sitting in our Reception area, how can you miss it?! We cannot wait to bring this exciting new equipment line to you as part of our promise to equip you with the absolute latest in fitness technology for ALL your fitness goals. Check it out today, this and more coming soon!

On the other end of all our exciting changes, comes our building construction works.

*IMPORTANT reminder for all our valued members:

Starting next Monday, 26th August, temporary Parking Adjustments will be in place that will result in the following temporary changes.

  • Commencing Monday, 26th August, several parking bays to the rear of the building will be restricted as we begin carpark works as part of our exciting building works.
  • Temporary fencing will be installed as we facilitate the trench work for the installation of the main services underground. Delivery of materials and machinery will commence this week, so please be mindful of these dedicated bays.
  • Entry and exit to the main driveway will also be modified. Access to the front carpark will be via the entry driveway in front of Repco only and to the rear, via Broadmeadows Street (which runs off Geelong Court).
  • The carpark area will have restricted access for approximately 14 days as we carry out these works.
  • Due to the scope of the works, RFX Athletic members please also be aware that the side rollerdoor will no longer be operational for any upcoming WODs.

We understand this may be a temporary inconvenience to you, but we promise it’s all part of a bigger, better plan for your future enjoyment. Your patience and co-operation is appreciated as we work towards making our facilities even more amazing!


Update : 12 August 2024

We have lots going on in and around the Club this week. Good news to members, there will be minimal (if any!) impact to your fitness routine.

An important reminder that we will have temporary Parking Adjustments starting in 2 weeks time, changes scheduled for Monday, 26thAugust. To ensure all our members are aware of these changes well in advance, please take note of the following temporary changes.

  • Commencing Monday, 26th August, several parking bays to the rear of the building will be restricted as we begin carpark works as part of our exciting building works. Temporary fencing will also be installed as we facilitate the trench work for the installation of the main services underground.
  • Entry and exit to the main driveway will also be modified. Access to the front carpark will be via the entry driveway in front of Repco only and to the rear, via Broadmeadows Street (which runs off Geelong Court). 
  • The carpark area will have restricted access for approximately 14 days as we carry out these works.

We understand this may be a temporary inconvenience to you, but we promise it’s all part of a bigger, better plan for your future enjoyment. Your patience and co-operation is appreciated as we work towards making our facilities even more amazing!


Update :  5 August 2024

Exciting times sure are ahead for our Bibra Lake members. But first, we are carrying out urgent repair works to our Steam Room after some unfortunate damage occurred. We are hoping to have this damage repaired by Wednesday, 7th August, however due to the scope of the repair work needed, this date cannot be confirmed at this time. A reminder for members, please abide by the terms and conditions for use to ensure these facilities remain accessible for all members enjoyment.

Next up, with main services needing to run into the new building works at the back of the building, we will closing down part of the Carpark. Starting Monday, 26th August, temporary fencing will be installed to facilitate trench work, along with the installation of electrical conduits. The carpark will have restricted access for approximately 14 days. Member access to the front carpark will be via the entry driveway in front of Repco. We ask all our members to please follow the directional signage and allow extra time to arrive before a class.

We understand this may be a temporary inconvenience to you, but we promise it’s all part of a bigger, better plan for your future enjoyment. Your patience and co-operation is appreciated as we work to make our facilities even more amazing for you as a Bibra Lake member.


Update : 22 July 2024

Construction continues into this week, but with minimal impact to our members.

Keep checking this page for the latest updates and exciting developments!


Update : 15 July 2024

Our first project works begin around the Outdoor Pool area. You will notice the install of some temporary fencing, along with the astro turf being lifted to make way for our new Outdoor Shower Block. From now and over the coming weeks, this will mean that no sun lounges will be available on the astro turf area next to the frangipani tree. You will still be able to access the Outdoor Pool, as well as being able to make use of the Outdoor Shower.

The best is yet to come!


 

LATEST NEWS & EVENTS

New Shower Block Now Open – Next Phase of Upgrades Begins!

Read More

RBG Early Closure – Thursday 5th December

Read More

Festive Opening Hours

Read More

Our Sleigh of Hope returns this Christmas

Read More